Every cost cell in the table, line by line: which part, for how much, from whom; which figure, resting on what. The numbers on this page are worked out from the simulation and the parts list, so when one changes the page does too. Only the pole price table is copied from its sources.
Row by row
Urban
19 units (18 lighting columns, 1 lighting column at a signalised junction), over 8,14 km².
| Line | Total | Per km² |
|---|---|---|
| Broadcast units | 26.547,75 TL | 3.261,39 TL |
| Structure and fitting | 47.500,00 TL | 5.835,38 TL |
| Standalone power | 0,00 TL | 0,00 TL |
| Build (CAPEX) | 74.047,75 TL | 9.096,78 TL |
| Electricity | 320,34 TL | 39,35 TL |
| Data plans | 0,00 TL | 0,00 TL |
| Rent | 0,00 TL | 0,00 TL |
| Replacement | 2.654,78 TL | 326,14 TL |
| Maintenance | 8.345,75 TL | 1.025,28 TL |
| Per diem | 0,00 TL | 0,00 TL |
| Share of central operation | 4.503,00 TL | 553,19 TL |
| Running, a year (OPEX) | 15.823,86 TL | 1.943,96 TL |
Rural
52 units (5 lighting columns, 47 distribution poles), over 354,00 km².
| Line | Total | Per km² |
|---|---|---|
| Broadcast units | 72.657,00 TL | 205,25 TL |
| Structure and fitting | 232.930,00 TL | 657,99 TL |
| Standalone power | 98.230,00 TL | 277,49 TL |
| Build (CAPEX) | 403.817,00 TL | 1.140,73 TL |
| Electricity | 84,30 TL | 0,24 TL |
| Data plans | 0,00 TL | 0,00 TL |
| Rent | 0,00 TL | 0,00 TL |
| Replacement | 19.553,38 TL | 55,24 TL |
| Maintenance | 84.775,25 TL | 239,48 TL |
| Per diem | 0,00 TL | 0,00 TL |
| Share of central operation | 12.324,00 TL | 34,81 TL |
| Running, a year (OPEX) | 116.736,93 TL | 329,77 TL |
Tunnel
51 units (51 tunnel brackets), over 2,00 km.
| Line | Total | Per km |
|---|---|---|
| Broadcast units | 70.757,91 TL | 35.378,96 TL |
| Structure and fitting | 239.190,00 TL | 119.595,00 TL |
| Standalone power | 0,00 TL | 0,00 TL |
| Build (CAPEX) | 309.947,91 TL | 154.973,96 TL |
| Electricity | 859,86 TL | 429,93 TL |
| Data plans | 0,00 TL | 0,00 TL |
| Rent | 0,00 TL | 0,00 TL |
| Replacement | 7.075,79 TL | 3.537,90 TL |
| Maintenance | 44.803,50 TL | 22.401,75 TL |
| Per diem | 0,00 TL | 0,00 TL |
| Share of central operation | 12.087,00 TL | 6.043,50 TL |
| Running, a year (OPEX) | 64.826,15 TL | 32.413,08 TL |
- The urban and rural rows are divided by the ground they serve and the tunnel by its length; the cells in the table are the last lines of this breakdown.
- Receivers are not in this breakdown. The application does not settle who buys them, so they never enter the per square kilometre figures.
Broadcast units: what one costs where
| One unit | Lighting column | Distribution pole | Rooftop | Tunnel bracket | Raised mast |
|---|---|---|---|---|---|
| Broadcast unit (at a thousand) | 1.397,25 TL | 1.397,25 TL | 1.397,25 TL | 1.387,41 TL | 1.397,25 TL |
| Fitting | 2.500,00 TL | 4.690,00 TL | 1.890,00 TL | 4.690,00 TL | 191.890,00 TL |
| Solar panel and battery | 0,00 TL | 2.090,00 TL | 0,00 TL | 0,00 TL | 2.090,00 TL |
| To build | 3.897,25 TL | 8.177,25 TL | 3.287,25 TL | 6.077,41 TL | 195.377,25 TL |
| Electricity | 16,86 TL | 0,00 TL | 16,86 TL | 16,86 TL | 0,00 TL |
| Rent | 0,00 TL | 0,00 TL | 24.500,00 TL | 0,00 TL | 0,00 TL |
| Maintenance | 439,25 TL | 1.757,00 TL | 318,50 TL | 878,50 TL | 1.757,00 TL |
| Replacement | 139,72 TL | 401,16 TL | 139,72 TL | 138,74 TL | 401,16 TL |
| Share of central operation | 237,00 TL | 237,00 TL | 237,00 TL | 237,00 TL | 237,00 TL |
| To run, a year | 832,84 TL | 2.395,16 TL | 25.212,08 TL | 1.271,10 TL | 2.395,16 TL |
The town and open country rows use the same broadcast unit: the amplified SX1280 module E28-2G4M20S, an outdoor 5 dBi rod antenna, the same microcontroller and secure element. In the tunnel the unit carries the DWM3000 UWB module. What differs is not the unit but the structure it goes on: a lighting column with mains in town, a distribution pole with no mains and a solar panel in open country, a bracket that waits on a lane closure in the tunnel.
On a raised mast the build costs 50 times what it does on a lighting column. The same unit on the same ground; the only difference is what it is fitted to.
Of the structures the table uses, a unit is cheapest to build and run on a town lighting column, yet the town row is the dearest per square kilometre. The reason is density: buildings cut the signal, so a unit serves 0,43 km² in town and 6,81 km² in open country. 19 units over 8,14 km² are 2,33 units a km²; 52 units over 354,00 km² are 0,15. The cost per square kilometre is the cost per unit times that density.
A structure gives two things: power and a line to the centre. A signalised junction carries a controller cabinet with both the mains and a line to the traffic management centre, which the municipality's cameras already use. A unit on a structure with a line reaches the centre over it: a signalised junction in town, the tunnel's communications spine in a tunnel, an ITS point on the road in open country. A unit with no line, such as one on a distribution pole far from an ITS point, keeps running on its solar panel and passes its messages by its own radio to the nearest unit that has a line; no unit carries a SIM card. Each unit sends the centre a short "still working" message at regular intervals, and a unit whose message stops coming is taken as failed and a crew is sent. When a receiver sees GPS jamming or spoofing it passes that to a nearby broadcast unit, and the warning reaches the centre the same way.
Adding units raises availability, but not for nothing. What the existing structures do is make that trade affordable, because each extra unit is a device and a fitting rather than a site.
Pole heights and prices
| Structure | Height | Price | Source |
|---|---|---|---|
| Lighting column, TEDAŞ-type galvanised polygonal | 6 / 8 / 10 / 12 / 14 / 15 m | 6.500 / 9.750 / 14.750 / 18.250 / 24.750 / 27.500 TL | Pana Bayrak Direği, September 2026 |
| Lighting column, galvanised road column | 8-10 m | 14.000-28.000 TL | Palmiye Aydınlatma, January 2026 |
| Galvanised pole | 20 / 30 m | 120.000 / 475.000 TL | Pana Bayrak Direği, September 2026 |
| Distribution pole, spun concrete | 9,3-25 m | not published | TEDAŞ specification MLZ/99-34 |
YERKON uses the pole that stands and buys none; these prices show what raising a new one costs and where the 25 m mast's figure comes from. The column heights come from TEDAŞ's road class table (6 to 14 m), the distribution pole lengths from TEDAŞ-MLZ/99-34; their sources are on the Regulation page.
YERKON broadcast unit prices
| Product | One | At a hundred | At a thousand |
|---|---|---|---|
| Urban and rural broadcast unit | 2.072,94 TL | 1.548,47 TL | 1.397,25 TL |
| Critical area broadcast unit | 2.298,01 TL | 1.641,36 TL | 1.387,41 TL |
| Pedestrian receiver | 3.960,43 TL | 3.204,94 TL | 2.697,22 TL |
| Vehicle receiver | 4.770,87 TL | 4.035,92 TL | 3.169,03 TL |
The parts of every broadcast unit and receiver
Urban and rural broadcast unit
| Part | What it does | Seller | One | At a hundred | At a thousand |
|---|---|---|---|---|---|
| EBYTE E28-2G4M20S | SX1280 radio module with an amplifier, 20 dBm | JLCPCB | 5,96 USD | 5,81 USD | 5,81 USD |
| STM32G031K8T6 | microcontroller, 64 KB | LCSC | 3,11 USD | 2,33 USD | 1,74 USD |
| Microchip ATECC608B | identity and key chip | DigiKey; Mouser (1.000+) | 0,90 USD | 0,90 USD | 0,82 USD |
| Taoglas GW.22.5151 | pole and vehicle antenna, 2,4 GHz, 5 dBi, IP67, outdoor | Westward Sales; Mouser (1.000+) | 11,51 USD | 11,51 USD | 10,07 USD |
| HI-LINK HLK-5M12 | mains supply, 230 V AC to 12 V DC, 5 W | LCSC | 2,84 USD | 1,78 USD | 1,59 USD |
| TI TPS563200DDCR | switching regulator, 12 V to 3,3 V, 3 A | LCSC | 1,03 USD | 0,72 USD | 0,67 USD |
| Littelfuse SMBJ18A | input surge protection (TVS) | LCSC | 0,15 USD | 0,12 USD | 0,10 USD |
| VDR-10D471K | mains-side varistor | LCSC | 0,12 USD | 0,10 USD | 0,07 USD |
| PTTC SMD1206P050TF/15 | resettable fuse, 500 mA | LCSC | 0,10 USD | 0,08 USD | 0,06 USD |
| MDD SS34 | reverse polarity diode | LCSC | 0,04 USD | 0,04 USD | 0,03 USD |
| 2 x Cixi Kefa KF301-5.0-2P | screw terminal, 2 way (supply and service) | LCSC | 0,20 USD | 0,15 USD | 0,12 USD |
| DreamLNK IPEX TO SMA | 20 cm cable from the module to the SMA on the box wall | LCSC | 1,05 USD | 0,64 USD | 0,54 USD |
| Gainta G203 | outdoor box, 115x65x40 mm, IP65 (4,99 €) | Gainta | 5,66 USD | 5,66 USD | 5,66 USD |
| Passives and indicator | 10 x 100 nF, 10 x 10 kΩ, 3 x 10 µF, 2 x 22 µF, LED, button (LCSC C1525, C25744, C15850, C45783, C2286, C318884) | LCSC | 0,79 USD | 0,60 USD | 0,43 USD |
| JLCPCB two-layer board | printed circuit board, two layers, up to 100x100 mm | JLCPCB | 0,40 USD | 0,40 USD | 0,40 USD |
| JLCPCB SMD dizgi, 125 nokta | SMD assembly, 125 joints: E28 16, STM32G031 32, ATECC608B 9, TPS563200 6, SMBJ 2, fuse 2, SS34 2, passives 56 | JLCPCB | 8,28 USD | 0,60 USD | 0,24 USD |
| JLCPCB lehim, 10 nokta | through-hole and lead soldering, 10 joints: HLK-5M12 4, varistor 2, two terminal blocks 4 | JLCPCB | 0,16 USD | 0,16 USD | 0,16 USD |
| Total | 2.072,94 TL | 1.548,47 TL | 1.397,25 TL |
Critical area broadcast unit
| Part | What it does | Seller | One | At a hundred | At a thousand |
|---|---|---|---|---|---|
| Qorvo DWM3000TR13 | UWB radio module | JLCPCB; DigiKey (25+) | 23,10 USD | 19,84 USD | 16,21 USD |
| STM32G031K8T6 | microcontroller, 64 KB | LCSC | 3,11 USD | 2,33 USD | 1,74 USD |
| Microchip ATECC608B | identity and key chip | DigiKey; Mouser (1.000+) | 0,90 USD | 0,90 USD | 0,82 USD |
| HI-LINK HLK-5M12 | mains supply, 230 V AC to 12 V DC, 5 W | LCSC | 2,84 USD | 1,78 USD | 1,59 USD |
| TI TPS563200DDCR | switching regulator, 12 V to 3,3 V, 3 A | LCSC | 1,03 USD | 0,72 USD | 0,67 USD |
| Littelfuse SMBJ18A | input surge protection (TVS) | LCSC | 0,15 USD | 0,12 USD | 0,10 USD |
| VDR-10D471K | mains-side varistor | LCSC | 0,12 USD | 0,10 USD | 0,07 USD |
| PTTC SMD1206P050TF/15 | resettable fuse, 500 mA | LCSC | 0,10 USD | 0,08 USD | 0,06 USD |
| MDD SS34 | reverse polarity diode | LCSC | 0,04 USD | 0,04 USD | 0,03 USD |
| 2 x Cixi Kefa KF301-5.0-2P | screw terminal, 2 way (supply and service) | LCSC | 0,20 USD | 0,15 USD | 0,12 USD |
| Gainta G203 | outdoor box, 115x65x40 mm, IP65 (4,99 €) | Gainta | 5,66 USD | 5,66 USD | 5,66 USD |
| Passives and indicator | 10 x 100 nF, 10 x 10 kΩ, 3 x 10 µF, 2 x 22 µF, LED, button (LCSC C1525, C25744, C15850, C45783, C2286, C318884) | LCSC | 0,79 USD | 0,60 USD | 0,43 USD |
| JLCPCB two-layer board | printed circuit board, two layers, up to 100x100 mm | JLCPCB | 0,40 USD | 0,40 USD | 0,40 USD |
| JLCPCB SMD dizgi, 133 nokta | SMD assembly, 133 joints: DWM3000 24, STM32G031 32, ATECC608B 9, TPS563200 6, SMBJ 2, fuse 2, SS34 2, passives 56 | JLCPCB | 8,29 USD | 0,62 USD | 0,25 USD |
| JLCPCB lehim, 10 nokta | through-hole and lead soldering, 10 joints: HLK-5M12 4, varistor 2, two terminal blocks 4 | JLCPCB | 0,16 USD | 0,16 USD | 0,16 USD |
| Total | 2.298,01 TL | 1.641,36 TL | 1.387,41 TL |
Pedestrian receiver
| Part | What it does | Seller | One | At a hundred | At a thousand |
|---|---|---|---|---|---|
| EBYTE E28-2G4M20S | SX1280 radio module with an amplifier, 20 dBm | JLCPCB | 5,96 USD | 5,81 USD | 5,81 USD |
| Qorvo DWM3000TR13 | UWB radio module | JLCPCB; DigiKey (25+) | 23,10 USD | 19,84 USD | 16,21 USD |
| Espressif ESP32-S3-WROOM-1-N8 | phone link (BLE) | LCSC | 4,91 USD | 3,43 USD | 3,24 USD |
| CEVA BNO085 | motion sensor | DigiKey; Mouser (1.000+) | 13,57 USD | 13,57 USD | 8,81 USD |
| Microchip ATECC608B | identity and key chip | DigiKey; Mouser (1.000+) | 0,90 USD | 0,90 USD | 0,82 USD |
| ZHONGKEWEI ATGM336H-5NR32 | satellite positioning module (GPS, GLONASS, BeiDou, QZSS) | JLCPCB | 2,53 USD | 1,66 USD | 1,50 USD |
| Abracon PRO-OB-430 | satellite positioning antenna, on the board, 1.575 and 1.602 MHz | JLCPCB | 1,09 USD | 0,69 USD | 0,59 USD |
| Zetta ZDEMMC04GA | storage, 4 GB eMMC | JLCPCB | 4,32 USD | 3,34 USD | 2,65 USD |
| Good Display GDEY0154D67 | 1,54 inch e-paper screen, 200x200, SPI | Good Display | 4,51 USD | 4,28 USD | 4,28 USD |
| Seeed Studio SKU 313070004 | solar panel, 0,5 W, 5,5 V, 55x70 mm | Seeed Studio | 2,50 USD | 2,50 USD | 2,50 USD |
| YDL 803040 | LiPo cell, 3,7 V, 1.000 mAh | YDL Battery | 4,27 USD | 4,27 USD | 4,27 USD |
| TOP POWER TP4056 | LiPo charger | LCSC | 0,19 USD | 0,15 USD | 0,11 USD |
| PUOLOP DW01A | battery protection IC | LCSC | 0,02 USD | 0,02 USD | 0,02 USD |
| Fortune FS8205 | battery protection MOSFETs | LCSC | 0,18 USD | 0,14 USD | 0,11 USD |
| Hroparts TYPE-C-31-M-12 | USB-C charge and service port | LCSC | 0,19 USD | 0,15 USD | 0,10 USD |
| TOREX XC6206P332MR-G | 3,3 V linear regulator | LCSC | 0,14 USD | 0,12 USD | 0,09 USD |
| XUNPU FPC-05F-24PH20 | e-paper screen connector, 24 pins, 0,5 mm | LCSC | 0,11 USD | 0,08 USD | 0,07 USD |
| AOS AO3400A | MOSFET of the e-paper booster | LCSC | 0,09 USD | 0,07 USD | 0,05 USD |
| XR XRNR201610-10uH/M | inductor of the e-paper booster, 10 µH | LCSC | 0,05 USD | 0,04 USD | 0,03 USD |
| 4 x Shikues MBR0530 | Schottky diode: three in the e-paper booster, one on the solar input | LCSC | 0,08 USD | 0,08 USD | 0,05 USD |
| Gainta G517G(BC)-1 | hand-held box with a battery bay, 92x66,5x21 mm (1,86 €) | Gainta | 2,11 USD | 2,11 USD | 2,11 USD |
| Passives and indicator | 10 x 100 nF, 10 x 10 kΩ, 3 x 10 µF, 2 x 22 µF, LED, button (LCSC C1525, C25744, C15850, C45783, C2286, C318884) | LCSC | 0,79 USD | 0,60 USD | 0,43 USD |
| JLCPCB two-layer board | printed circuit board, two layers, up to 100x100 mm | JLCPCB | 0,40 USD | 0,40 USD | 0,40 USD |
| JLCPCB SMD dizgi, 428 nokta | SMD assembly, 428 joints: E28 16, DWM3000 24, ESP32-S3 41, BNO085 28, ATECC608B 9, ATGM336H 18, satellite antenna 2, eMMC 153, screen connector 26, TP4056 9, DW01A 6, FS8205 8, USB-C 16, XC6206 3, AO3400A 3, inductor 2, 4 diodes 8, passives 56 | JLCPCB | 8,77 USD | 1,09 USD | 0,73 USD |
| JLCPCB lehim, 4 nokta | through-hole and lead soldering, 4 joints: battery and solar panel leads 4 | JLCPCB | 0,07 USD | 0,07 USD | 0,07 USD |
| Total | 3.960,43 TL | 3.204,94 TL | 2.697,22 TL |
Vehicle receiver
| Part | What it does | Seller | One | At a hundred | At a thousand |
|---|---|---|---|---|---|
| EBYTE E28-2G4M20S | SX1280 radio module with an amplifier, 20 dBm | JLCPCB | 5,96 USD | 5,81 USD | 5,81 USD |
| Qorvo DWM3000TR13 | UWB radio module | JLCPCB; DigiKey (25+) | 23,10 USD | 19,84 USD | 16,21 USD |
| Artery AT32F403ARGT7 | microcontroller, 1 MB, SD/MMC and CAN | JLCPCB | 2,35 USD | 1,72 USD | 1,30 USD |
| CEVA BNO085 | motion sensor | DigiKey; Mouser (1.000+) | 13,57 USD | 13,57 USD | 8,81 USD |
| Microchip ATECC608B | identity and key chip | DigiKey; Mouser (1.000+) | 0,90 USD | 0,90 USD | 0,82 USD |
| TI TCAN1051HGVDRQ1 | CAN transceiver | LCSC; Mouser (1.000+) | 1,98 USD | 1,87 USD | 1,19 USD |
| ILI9341 SPI TFT, 2,8" | 2,8 inch display | Elecrow; Alibaba (1.000+) | 10,90 USD | 10,90 USD | 6,00 USD |
| Taoglas GW.22.5151 | pole and vehicle antenna, 2,4 GHz, 5 dBi, IP67, outdoor | Westward Sales; Mouser (1.000+) | 11,51 USD | 11,51 USD | 10,07 USD |
| ZHONGKEWEI ATGM336H-5NR32 | satellite positioning module (GPS, GLONASS, BeiDou, QZSS) | JLCPCB | 2,53 USD | 1,66 USD | 1,50 USD |
| Abracon PRO-OB-430 | satellite positioning antenna, on the board, 1.575 and 1.602 MHz | JLCPCB | 1,09 USD | 0,69 USD | 0,59 USD |
| Zetta ZDEMMC04GA | storage, 4 GB eMMC | JLCPCB | 4,32 USD | 3,34 USD | 2,65 USD |
| XLSEMI XL7015E1 | regulator from the vehicle supply (up to 80 V) to 3,3 V | LCSC | 0,50 USD | 0,30 USD | 0,23 USD |
| Brightking SMBJ33A | surge protection on the vehicle input (TVS) | LCSC | 0,07 USD | 0,06 USD | 0,05 USD |
| PTTC SMD1206P050TF/15 | resettable fuse, 500 mA | LCSC | 0,10 USD | 0,08 USD | 0,06 USD |
| MDD SS34 | reverse polarity diode | LCSC | 0,04 USD | 0,04 USD | 0,03 USD |
| 2 x Cixi Kefa KF301-5.0-2P | screw terminal, 2 way (supply and service) | LCSC | 0,20 USD | 0,15 USD | 0,12 USD |
| Hroparts TYPE-C-31-M-12 | USB-C charge and service port | LCSC | 0,19 USD | 0,15 USD | 0,10 USD |
| DreamLNK IPEX TO SMA | 20 cm cable from the module to the SMA on the box wall | LCSC | 1,05 USD | 0,64 USD | 0,54 USD |
| Gainta G212 | vehicle box, 115x90x55 mm, IP65 (5,98 €) | Gainta | 6,79 USD | 6,79 USD | 6,79 USD |
| Passives and indicator | 10 x 100 nF, 10 x 10 kΩ, 3 x 10 µF, 2 x 22 µF, LED, button (LCSC C1525, C25744, C15850, C45783, C2286, C318884) | LCSC | 0,79 USD | 0,60 USD | 0,43 USD |
| JLCPCB two-layer board | printed circuit board, two layers, up to 100x100 mm | JLCPCB | 0,40 USD | 0,40 USD | 0,40 USD |
| JLCPCB SMD dizgi, 409 nokta | SMD assembly, 409 joints: E28 16, DWM3000 24, AT32F403A 64, BNO085 28, ATECC608B 9, TCAN1051 8, ATGM336H 18, satellite antenna 2, eMMC 153, XL7015 9, SMBJ 2, fuse 2, SS34 2, USB-C 16, passives 56 | JLCPCB | 8,74 USD | 1,06 USD | 0,69 USD |
| JLCPCB lehim, 18 nokta | through-hole and lead soldering, 18 joints: the screen module's 14-pin header 14, two terminal blocks 4 | JLCPCB | 0,30 USD | 0,30 USD | 0,27 USD |
| Total | 4.770,87 TL | 4.035,92 TL | 3.169,03 TL |
Where the prices came from
- Every part carries its seller's own price ladder: the main parts and the rest of the unit, that is the mains supply, regulator, protection, terminals, antenna cable, box, passives, the printed board, its assembly and soldering. Where a unit holds more than one of a part (terminals, passives), the tier is the one the pieces for that many units reach.
- Where a seller published no tier for a quantity, no discount is assumed and the last known tier holds. The boxes are priced on request above a hundred, and no volume price could be read for the printed board or the battery; those enter at their one-unit price at every quantity. Assembly setup, stencil and part loading fees are paid once an order, so each unit's share shrinks as the order grows. The cost table uses the thousand.
- The part prices are the sellers' list prices of 25 to 28 September 2026; the links are above. They are to be confirmed by quotation before ordering. If a price changes, this page and the table follow on their own.
What every figure rests on
The crew and its day
One crew day: 17.570 TL/day (worked out)
A day of the fitting and maintenance crew: bucket truck 2.000 TL x 8 hours x 0,7 = 11.200 TL (a certified operator comes with the hire); electrician, a thirtieth of the middle of the monthly range, 95.000 TL, 3.170 TL; helper, the large-city top of the band, 3.200 TL. 17.570 TL in all. A maintenance visit is this divided by the sites the crew reaches on that structure in a day: 17.570 / 8 = 2.196 TL on a lighting column, 17.570 / 4 = 4.392 TL on a rural distribution pole and in a tunnel. A roof needs no bucket truck: 6.370 / 4 = 1.592 TL.
Source: bucket truck: a 20 m bucket truck is about 2.000 TL an hour in Ankara, 30 % off by the day (Ankara Sepetli Vinç Kiralama, price guide, 2026); labour: an electrician 80.000-110.000 TL a month, a labourer 2.500-3.200 TL a day, near the top in large cities (Yapı Arenası, 12 August 2026)
Ankara Sepetli Vinç Kiralama: price guide (a 20 m bucket truck about 2.000 TL an hour, 30 % off by the day) · Yapı Arenası: 2026 trade wages (12 August 2026)
Maintenance crew: 2 people (worked out)
How many people are paid a per diem: the electrician and helper priced into the crew day. The bucket truck's operator comes with the hire, and the hire company pays that person's per diem.
Source: the crew in the crew day: an electrician and a helper (Yapı Arenası, 12 August 2026); the bucket truck's operator belongs to the hire company
A crew day on roofs: 6.370 TL (worked out)
A crew day on roofs: no bucket truck, the roof is reached by the stairs. Electrician, a thirtieth of the middle of the monthly range, 95.000 TL, 3.170 TL; helper, the large-city top of the band, 3.200 TL. 6.370 TL in all.
Source: labour: an electrician 80.000-110.000 TL a month, a labourer 2.500-3.200 TL a day, near the top in large cities (Yapı Arenası, 12 August 2026)
Sites a crew covers in a day
Lighting columns: 8 sites/day (worked out)
How many lighting columns a crew fits or visits in a day. A published example: 11 crews replaced 414 luminaires on 207 poles over one weekend, 18,8 poles and 37,6 luminaires a crew. The report does not give the hours, only that the work ran day and night; counting 12 hours of each of the two days, a crew replaced 1,6 luminaires an hour, 12,5 in an eight-hour day. A YERKON unit is one clamp and one supply tap on a column, no more work than a luminaire. 8 a day is a cautious figure below that; an hour a column.
Source: Dicle Elektrik, Diyarbakır Suriçi, 25 June 2026: 11 crews with 11 bucket trucks replaced 414 luminaires on 207 poles over one weekend
Rural distribution poles: 4 sites/day (worked out)
How many distribution poles a crew reaches in a day in open country. Town counts an hour of work a column (columns a crew reaches in a day, the Dicle Elektrik example). Open country adds the road: two hours of the eight-hour day to and from the base, half an hour between sites (YERKON's estimate of the road). (8 - 2) / (1 + 0,5) = 4.
Source: Dicle Elektrik, Diyarbakır Suriçi, 25 June 2026: 11 crews with 11 bucket trucks replaced 414 luminaires on 207 poles over one weekend
Tunnel: 4 sites/day (worked out)
How many units a crew fits or visits in a tunnel in a day. The work waits on the highways authority's lane closure, whose setting up and taking down takes part of the day. The work per unit is about an hour as in town (the Dicle Elektrik example); the time lost to the closure is counted like the road in open country: 4 a day.
Source: Dicle Elektrik, Diyarbakır Suriçi, 25 June 2026: 11 crews with 11 bucket trucks replaced 414 luminaires on 207 poles over one weekend
Roofs: 4 sites/day (worked out)
How many roofs a crew reaches in a day. The work on a roof is as much as on a column (about an hour, the Dicle Elektrik example), but each building needs its manager found for the permission and the key; that wait is counted like the road: 4 a day.
Source: Dicle Elektrik, Diyarbakır Suriçi, 25 June 2026: 11 crews with 11 bucket trucks replaced 414 luminaires on 207 poles over one weekend
Raised masts: 4 sites/day (worked out)
How many 25 m masts a crew reaches in a day. A 20 m bucket truck falls short, so the mast is climbed; masts stand far apart. The same figure as a rural distribution pole.
Source: Dicle Elektrik, Diyarbakır Suriçi, 25 June 2026: 11 crews with 11 bucket trucks replaced 414 luminaires on 207 poles over one weekend
Fitting
Fitting to a lighting column: 2.500 TL (worked out)
One crew day: bucket truck 2.000 TL x 8 hours x 0,7 = 11.200 TL; electrician, a thirtieth of the middle of the monthly range, 95.000 TL, 3.170 TL; helper, the large-city top of the band, 3.200 TL. 17.570 TL in all. A crew fits eight units a day to columns that already stand (columns a crew reaches in a day, from the Dicle Elektrik example): 17.570 / 8 = 2.196 TL; stainless clamps, cable and a fuse 300 TL. 2.496, rounded to 2.500 TL. The enclosure and power supply are inside the unit.
Source: bucket truck: a 20 m bucket truck is about 2.000 TL an hour in Ankara, 30 % off by the day (Ankara Sepetli Vinç Kiralama, price guide, 2026); labour: an electrician 80.000-110.000 TL a month, a labourer 2.500-3.200 TL a day, near the top in large cities (Yapı Arenası, 12 August 2026)
Ankara Sepetli Vinç Kiralama: price guide (a 20 m bucket truck about 2.000 TL an hour, 30 % off by the day) · Yapı Arenası: 2026 trade wages (12 August 2026)
Fitting to a distribution pole: 4.690 TL (worked out)
One crew day: bucket truck 2.000 TL x 8 hours x 0,7 = 11.200 TL; electrician, a thirtieth of the middle of the monthly range, 95.000 TL, 3.170 TL; helper, the large-city top of the band, 3.200 TL. 17.570 TL in all. The sites are kilometres apart, so a crew fits four a day (poles a crew reaches in a day): 17.570 / 4 = 4.392 TL; clamps and cable 300 TL. 4.692, rounded to 4.690 TL. The panel and battery are priced apart: the solar panel and battery.
Source: bucket truck: a 20 m bucket truck is about 2.000 TL an hour in Ankara, 30 % off by the day (Ankara Sepetli Vinç Kiralama, price guide, 2026); labour: an electrician 80.000-110.000 TL a month, a labourer 2.500-3.200 TL a day, near the top in large cities (Yapı Arenası, 12 August 2026)
Ankara Sepetli Vinç Kiralama: price guide (a 20 m bucket truck about 2.000 TL an hour, 30 % off by the day) · Yapı Arenası: 2026 trade wages (12 August 2026)
Fitting to a roof: 1.890 TL (worked out)
No bucket truck: the roof is reached by the stairs. An electrician 3.170 TL and a helper 3.200 TL, four roofs a day because of permission and access (roofs a crew reaches in a day): 6.370 / 4 = 1.592 TL; a bracket, cable and a tap into the building's supply 300 TL. 1.892, rounded to 1.890 TL.
Source: labour: an electrician 80.000-110.000 TL a month, a labourer 2.500-3.200 TL a day, near the top in large cities (Yapı Arenası, 12 August 2026)
Tunnel bracket: 4.690 TL (worked out)
One crew day: bucket truck 2.000 TL x 8 hours x 0,7 = 11.200 TL; electrician, a thirtieth of the middle of the monthly range, 95.000 TL, 3.170 TL; helper, the large-city top of the band, 3.200 TL. 17.570 TL in all. In the tunnel the work depends on the highways authority's lane closure, so a crew fits four a day (tunnel units a crew reaches in a day): 17.570 / 4 = 4.392 TL; a stainless bracket, units and cable 300 TL. 4.692, rounded to 4.690 TL. The closure itself is timed to the authority's maintenance closures and not priced apart.
Source: bucket truck: a 20 m bucket truck is about 2.000 TL an hour in Ankara, 30 % off by the day (Ankara Sepetli Vinç Kiralama, price guide, 2026); labour: an electrician 80.000-110.000 TL a month, a labourer 2.500-3.200 TL a day, near the top in large cities (Yapı Arenası, 12 August 2026)
Ankara Sepetli Vinç Kiralama: price guide (a 20 m bucket truck about 2.000 TL an hour, 30 % off by the day) · Yapı Arenası: 2026 trade wages (12 August 2026)
Raising a mast: 191.890 TL (worked out)
A twenty-five metre mast and its fitting. No price is published for 25 m; the 20 m pole's price is carried to 25 m by the simulation's mast rule (cost grows with the square of height): 120.000 x (25 / 20)² = 187.500 TL. The 30 m price rises faster than that rule (475.000 TL), so this value errs low. Fitting is a quarter of a crew day, 4.392 TL: 191.892, rounded to 191.890 TL. The foundation and crane are not priced apart.
Source: Pana Bayrak Direği (Ankara), September 2026 list prices: a 20 m galvanised pole 120.000 TL, a 30 m galvanised pole 475.000 TL; TEDAŞ-type galvanised polygonal columns 6 m 6.500, 8 m 9.750, 10 m 14.750, 12 m 18.250, 14 m 24.750, 15 m 27.500 TL
How high the unit stands
On a lighting column: 12 m (standard)
How tall the lighting column a unit stands on is. In TEDAŞ's table the heights are a set, 6, 8, 10, 12, 14 m, by road class. Kızılay's main streets are M1 to M3, so 10 to 14 m; 12 m is the middle of that. The town row was run at every value of the set (29 September 2026): at 8 m HPE P95 9,07 m, availability 94,96 %, CAPEX 10.093 TL/km²; at 10 m 8,83 m, 96,18 %, 9.373 TL/km²; at 12 m the table's own figures; at 14 m 8,67 m, 96,82 %, 8.990 TL/km². Availability and cost improve smoothly with height and P95 does not: P95 at 12 m is higher than at 10 m and 14 m. P95 is the tail of eight shadow draws, so it moves this much.
Source: TEDAŞ, rules for LED road lighting design (August 2022), annex 1: columns 12 to 14 m on M1 roads, 10 to 12 m on M2 and M3, 8 to 10 m on M4, 8 m on M5, 6 to 8 m on footways
On a distribution pole: 10 m (assumption)
How high a unit stands on a rural distribution pole: the pole's height above ground less 2,5 m to the medium-voltage conductors. The pole lengths are a set (TEDAŞ) and the distance comes from the regulation; no source was found for how much of the pole is buried, so the value is still an assumption. The rural row was run at three heights on the same placement (29 September 2026): at 6 m HPE P95 8,67 m, availability 91,00 %, area 327,50 km², CAPEX 1.233 TL/km²; at 8 m 8,22 m, 93,26 %, 344,58 km², 1.172 TL/km²; at 10 m the table's own figures. The lower the unit, the less it covers and the less often it gives a position.
Source: pole lengths: TEDAŞ-MLZ/99-34, spun concrete pole specification (9,3-10-11 m, 12-13-14 m, 15-16 m and up); distance from the conductors: the Regulation on Electrical Power Installations, least vertical distance from overhead conductors to communication lines 2,5 m at medium voltage and 1 m at low voltage; no source was found for the buried depth
TEDAŞ-MLZ/99-34: spun concrete pole specification, September 2017 (lengths 9,3 to 25 m) · Regulation on Electrical Power Installations (least vertical distance to communication lines: 1 m at low voltage, 2,5 m at medium voltage)
On a roof: 2 m (assumption)
How far the roof bracket lifts the unit above the roof. The unit's height above the ground is the building's own height plus this; the building's height is read from the fetched footprints, one building at a time.
Source: YERKON assumption
On a raised mast: 25 m (assumption)
Purpose-built mast. 25 m is the height a 10 km link needs against a 2 m vehicle antenna over flat ground.
Source: YERKON assumption
Power
One unit's yearly consumption: 3 kWh/year (worked out)
One broadcast unit's yearly consumption. The unit spends nearly all its time listening: the SX1280 draws a few mA doing that and the microcontroller one or two, under 30 mW together at 3,3 V. With the mains converter's idle loss and the replies it sends, the average stays under 0,34 W, which is 3 kWh a year. That is a generous upper bound.
Source: SX1280 and STM32G0 datasheets, YERKON's arithmetic
Electricity tariff: 5,62 TL/kWh (worked out)
What a unit's electricity costs a kilowatt-hour. A unit cannot draw from a lighting column's public lighting circuit for free: the General Lighting Regulation allows no energy from that connection for any purpose other than public lighting; the unit counts as a separately metered commercial subscriber. 4,78 x 1,175 = 5,62 TL/kWh.
Source: commercial, low voltage, single rate, taxes included 4,78 TL/kWh, January 2026 (forelektrik.com, 26 December 2025); the increase from 4 April 2026, low-voltage public and private services 17,5 % (Milliyet Uzmanpara, 4 April 2026)
General Lighting Regulation (no energy from the connection for any purpose but public lighting) · forelektrik.com: what a kWh costs, 2026 (commercial, single rate, taxes included 4,78 TL/kWh), 26 December 2025 · Milliyet Uzmanpara: the April 2026 electricity increase (low-voltage public and private services 17,5 %), 4 April 2026
Solar panel and battery: 2.090 TL (worked out)
Panel, battery, controller, bracket, box and cable for a unit on a structure with no mains. A 0,34 W load needs 8 Wh a day: a 10 W panel gives that on two hours of full sun in an Ankara winter, and an 84 Wh battery carries five days. Panel 518,72 + battery 524,40 + controller 276,67 + bracket 421,01 + an IP65 box for the battery and controller 147,41 + 5 m of cable at the top price of 40 TL a metre, 200 = 2.088,21, rounded to 2.090 TL.
Source: Akakçe, September 2026, the cheapest found: 10 W solar panel 518,72 TL; 12 V 7 Ah sealed battery 524,40 TL; 10 A PWM charge controller 276,67 TL; ABS solar panel mounting bracket set 421,01 TL; Çet-San thermoplastic surface box 260x180x75, IP65, 147,41 TL; 4 mm² solar cable 25-40 TL a metre (Power Enerji, solar cable prices 2026)
Akakçe: 10 W solar panel (cheapest 518,72 TL), September 2026 · Akakçe: 12 V 7 Ah sealed battery (cheapest 524,40 TL), September 2026 · Akakçe: 10 A PWM solar charge controller (cheapest 276,67 TL), September 2026 · Akakçe: solar mounting equipment (ABS panel bracket set 421,01 TL), September 2026 · Akakçe: Çet-San thermoplastic surface box 260x180x75 (147,41 TL), September 2026 · Power Enerji: solar cable prices 2026 (4 mm² 25-40 TL a metre)
Maintenance and per diem
Maintenance visits a year: 0,20 visits/year (design choice)
How often a unit is visited a year. The central system sees every unit's status (each unit sends a regular "still working" message), so a crew goes when one fails rather than by the calendar. One failure in five years is a pessimistic figure for a sealed board.
Source: YERKON design choice
Extra off-grid visits: 0,20 visits/year (worked out)
The extra attendance an off-grid site needs: the battery is replaced every five years (the battery's life), so 1 / 5 = 0,2 visits a year; the panel is cleaned on that visit.
Source: Turkish Revenue Administration depreciation list, 3.14.7: accumulators, 5 years, 20 %
Per diem, a person a day: 850 TL/day (standard)
The full daily allowance of one crew member for a day spent outside the place of duty. Under Travel Allowance Law 6245 it is paid to someone sent on a temporary duty outside the place of duty; in the private sector the tax-exempt part follows Income Tax Law 193, Article 24(2): the allowance of a civil servant on the same salary level. The schedule gives 850 TL for grades 5-15; a field technician's pay falls in that range, so that line is taken. On a day trip only part of it is paid: the share of the allowance on a day trip.
Source: Law 7567, 2026 Central Government Budget, Schedule H, B-e: grades 5-15, domestic daily allowance 850 TL
Travel Allowance Law 6245: place of duty (Article 3(g)), allowance on a day trip (Article 39) · Income Tax Law 193, Article 24(2): the tax-exempt part of daily allowances · Presidency of Strategy and Budget: 2026 Central Government Budget Law No. 7567, Schedule H (domestic daily allowances; grades 5-15, 850 TL)
Share of it on a day trip: 0,33 fraction (standard)
A maintenance visit is a day trip: the crew leaves in the morning and is back in the afternoon, so it spends the lunch time away: a third of the allowance (283,33 TL a person). Past 19:00 it would be two thirds.
Source: Travel Allowance Law 6245, Article 39: a third of the daily allowance for one of the lunch (13:00) or dinner (19:00) times away, two thirds for both, all of it for a night
Travel Allowance Law 6245: place of duty (Article 3(g)), allowance on a day trip (Article 39)
Does the town crew leave its duty station: no (design choice)
No. Travel Allowance Law, Article 3(g): in a metropolitan province the place of duty is the district the worker belongs to and the built-up area that continues it. A crew based in Çankaya serves Kızılay; no allowance inside the place of duty (Article 39).
Source: YERKON design choice, the maintenance crew is based in central Ankara
Travel Allowance Law 6245: place of duty (Article 3(g)), allowance on a day trip (Article 39)
Does the open-country crew leave its duty station: no (design choice)
No: a local technical firm in Polatlı does the maintenance, no crew travels from Ankara and there is no per diem. It does not rest on the distribution company's crews, because the company may not want the work. The poles are still the company's: climbing one may need its permission and conditions, to be settled in the public protocol.
Source: maintenance model: a local technical firm
Does the tunnel crew leave its duty station: no (design choice)
No: a local technical firm in Kızılcahamam does the maintenance, no per diem. Entering the bore and closing a lane still need the highways authority's permission; visits can be timed to its maintenance closures.
Source: maintenance model: a local technical firm
Rent and data
Distribution pole rent, a year: 0 TL/year (design choice)
What the distribution company charges a year to carry a unit on its pole: nothing. The units go up under a public-sector agreement, with the prospect of being included in public structures that already stand, such as ITS cabinets, roadside units and distribution poles. Nor has any distribution company published a fee for equipment on its poles: the transport ministry's rights-of-way rules, Türk Telekom's connection fees and the General Lighting Regulation name no per-pole fee. Fees charged to commercial users, for comparison: distribution companies have rented advertising space on their poles since 2015 with the regulator's leave, the smallest poster 4.700 TL a month (Tr724, 11 May 2019); Istanbul Metropolitan Municipality's 2025 tariff charges 24.500 TL a year for a repeater or small cell on its property, and twice the site selection fee for a cabinet on a BEDAŞ or AYEDAŞ lighting column. Without the agreement, 1.200 TL a pole a year would raise rural OPEX by about half.
Source: YERKON design choice: a public-sector agreement
Transport ministry: rules applying the rights-of-way regulation (no per-pole fee) · General Lighting Regulation (no energy from the connection for any purpose but public lighting) · Tr724: advertising on electricity poles (distribution companies have rented pole space since 2015, the smallest poster 4.700 TL a month), 11 May 2019 · Istanbul Metropolitan Municipality, electronic systems, 2025 tariff (yearly site fee for a repeater or small cell)
Roof rent, a year: 24.500 TL/year (published price)
What the building's owner is paid a year for the roof. No published tariff for a private roof was found; the nearest published fee is the 24.500 TL a year Istanbul Metropolitan Municipality charges for a small radio device. On public buildings the ceiling comes from Law 3194, additional article 9/7: 137.517,20 TL a year in a metropolitan province, 82.510,32 TL elsewhere. Roofs are rented, so the placement search does not offer them; this figure touches no row of the table.
Source: Istanbul Metropolitan Municipality, electronic systems, 2025 tariff: 24.500 TL a year for a repeater or small cell on its property
Istanbul Metropolitan Municipality, electronic systems, 2025 tariff (yearly site fee for a repeater or small cell) · Ministry of Agriculture and Forestry: 2025 base station rent rates (site selection fee 27.503,44 TL; cap of Law 3194, Additional Article 9(7))
Cellular data line, a year: 0 TL/year (design choice)
What a year of data costs a unit with no line of its own: nothing, because no unit carries a SIM card. A unit on a structure with a line reaches the centre over it: the tunnel's communications spine in a tunnel, a signalised junction's cabinet in town, an ITS point on the road in open country. A unit with no line passes its messages by its own radio to the nearest unit that has one. Each unit sends the centre a short "still working" message at regular intervals, and a unit whose message stops coming is taken as failed. When a receiver sees GPS jamming or spoofing it passes that to a nearby broadcast unit, and the warning reaches the centre the same way.
Source: YERKON design choice
Service life and the central system
A unit's service life: 10 years (standard)
How many years a unit lasts before it is replaced. A unit is a radio system, and the tax rules give that 10 years. The positioning line (3.49.8, 5 years) is for devices that locate by satellite, which an unit does not.
Source: Turkish Revenue Administration depreciation list, 3.49.4: radio telephone, telegraph or broadcast receiving devices and systems, 10 years, 10 %
The battery's life: 5 years (standard)
The battery's useful life.
Source: Turkish Revenue Administration depreciation list, 3.14.7: accumulators, 5 years, 20 %
Central system, a unit a year: 237 TL/year (worked out)
Each unit's yearly share of running the central management system. The system is the software that watches the units' records and tells the crew of a failure, and the person who runs it. One day a week of a developer: 95.000 x 12 x 0,2 = 228.000 TL; two servers backing each other up: 2 x 374,90 x 12 = 8.998 TL. 236.998, rounded to 237.000 TL a year. One person one day a week and two servers can watch the records of a thousand units, and the table prices the units at a thousand. So the cost is split across a thousand units: 237.000 / 1.000 = 237 TL a year. One day a week and a thousand units are YERKON's operating choice.
Source: median developer salary, companies in Türkiye, net 95.000 TL a month (Yazılımcı Maaşları 2026 survey, February 2026, 1.223 respondents); a 6 vCPU, 8 GB virtual server 374,90 TL a month (Karekod, cheapest VDS prices, 25 September 2026)
Yazılımcı Maaşları 2026 survey (1.223 respondents, net median 95.000 TL at companies in Türkiye), February 2026 · Karekod: cheapest VDS prices 2026 (6 vCPU, 8 GB, 374,90 TL a month), 25 September 2026